On Monday, the Metropolitan Transportation Authority (MTA) released an 11-page slideshow “overview” partially summarizing the details of its nearly $55 billion 2020-2024 capital plan. The unveiling seemed like Christmas morning - according to MTA CEO/Chair Pat Foye, the plan will sell itself. Everyone will get the pony that they asked for. NYCT President Andy Byford was “ecstatically happy” and elected officials and advocates were told they’d get their top priorities, ranging from costly expansion projects to new subway and commuter rail cars, buses, signals, and elevators.
Who wouldn’t want a huge infusion of funds into a century old, workworn transit system? We too want to believe! Unfortunately, the numbers just do not add up.
We question both the availability of the funding coming in and the ability of the MTA to spend this massive outlay. Historically, transit advocacy has centered on finding funds, but last year we started looking at actual expenses -- not “commitments” or authorizations to spend, as the MTA does. We found that the real constraint on MTA capital plans has become the ability to spend, not finding funding. (A related problem is keeping costs down so that what can be spent is done so efficiently.)
This plan is really Governor Cuomo’s. He controls the MTA, as described in great detail in our OpenMTA report. There are a few reasons we think his $55 billion “five-year” plan is not tethered to reality. While the Governor’s plan shows that he wants the MTA to spend 70% more on its 2020-2024, the MTA’s capacity to spend that much will not grow nearly as quickly.
In 2018, the MTA spent a record $6.6 billion on capital projects. However, only $4 billion of that was for current projects -- the other $2.6 billion was to complete projects from previous plans.
For about two decades the MTA has gotten further and further behind spending its capital funding. As a result, there is a growing hangover of past-year projects that must be completed every year. We estimate there will be at least $20 billion worth of 2015-2019 projects for the MTA to finish during the 2020-2024 plan.
Let’s assume the MTA can keep capital spending at the record pace of $6.6 billion a year. If it finishes the 2015-2019 plan in five more years, spending an average of $4 billion of the $20 billion per year, it leaves only $2.6 billion a year for 2020-2024 projects. And wait, the MTA still hasn’t finished the 2005-2009 or 2010-2014 plans. Clearly, something is off here.
We believe that projects that will not be built for at least a decade are more aspirational than real. By promising everything to everyone, the Governor is actually making it impossible to know which projects are real and which are not.
Given what was released this week is still technically a draft (and we’ve still only seen an outline, not a full plan) that must be approved by the MTA Board and Capital Program Review Board (CPRB), there is still time for the MTA to release a real implementation plan showing how it intends to finish this new plan along with all its current projects.
How Much Can the MTA Really Spend On a Five-Year Plan During the Plan?
Bluntly, we think it will be difficult for the MTA to spend even half of the $55 billion proposed for the 2020-2024 plan during that five-year period. MTA capital plans often taking more than 10 years to be completed. While this is not a new challenge, a capital program of nearly $55 billion is unprecedented and presents a good opportunity to figure out how to fix this ongoing structural MTA problem.
The MTA’s ability to spend capital dollars during plan years has decreased, not increased. In 2018, the MTA spent $6.6 billion on capital projects, but only $4 billion was for 2015-2019 projects. The MTA’s best-ever year for spending on projects from the current capital plan was in 2009, when it spent nearly $4.5 billion (see chart below).
With the 2015-2019 plan’s late start in 2016, there is a lot of work still left to do on that plan. The 2015-2019 plan has $33 billion worth of projects, but the MTA has only received $12 billion in funds as of June 31 of this year, and as of the end of 2018, only $20 billion worth of projects were committed. (A commitment is not the same as actually spending the money, it is the intent to use employees to complete a project or execution of a contract).
Can the MTA effectively manage more than $6.6 billion a year total in capital spending?
Given the MTA’s limited spending capacity, questions about the credibility of delivering a nearly $55 billion capital plan are warranted. With the recently-approved MTA reorganization, consolidating capital construction staff to headquarters will mean that the MTA will have to do even more with even less. Whether centralization will indeed lead to meaningful efficiencies will take time to determine.
Even if we give the MTA the benefit of the doubt and it does as well as it has in the past, getting $4.5 billion out the door every year, it will take 12 years to finish the 2020-2024 plan. This is all while it has a lot more to do on the current, 2015-2019 plan.
Given the limited ability to manage projects, what will the MTA prioritize?
The slideshow proposes what would be the largest investment in signals for MTA New York City Transit ever, at $7.1 billion. This comes with other large investments for elevators and subway cars, all while large expansion projects are continuing, such as East Side Access and LIRR Third Track.
With limited spending and staff capacity, the MTA will have to choose which projects come first and which come last. Janno Lieber, the MTA’s head of capital construction, has said that signals will come in the five-year window, but as of now, the MTA has not released an implementation plan or detailed project list with schedules of when it will commit to projects, as it has shown in prior plans.
Revenue Dependent on New Federal, State and City Fundings
The nearly $55 billion plan outline makes a number of big assumptions about funding that has not yet been secured. New funding is supposed to come from the federal government ($10.7 billion), the state government ($3 billion), and city government ($3 billion), totalling nearly $17 billion. These numbers are not real until the cash actually arrives from all parties involved.
Is it realistic to expect $10 billion in federal aid?
Under a Democratic president, the federal government contributed $7 billion to the last capital plan. This plan assumes even more federal dollars will come in, including a large contribution for Second Avenue Subway Phase 2: $2.9 billion alone. The feds provided $1.3 billion for Phase 1, so this would double that contribution to this project. While the President indicated support for the project via Twitter, a tweet is not a funding commitment of $2.9 billion.
Is it realistic to expect the state to provide $3 billion in direct aid?
While Governor Cuomo has said the state will provide $3 billion to the new plan, this is subject to legislative approval. The proposal of the Mayor’s match of $3 billion is also under review. Meanwhile, the state still owes $7.3 billion to the MTA for the 2015-2019 plan: it had pledged $8.3 billion in 2016 and only $1 billion has come in so far.
State Comptroller Tom DiNapoli, in his recent report on the MTA’s finances, noted that the remaining $7.3 billion will not start to come in until next fiscal year (beginning April 2020). The state also may not provide this as direct aid. It could authorize the MTA to issue its own bonds based on existing or new revenue, meaning that the impact on the MTA and taxpayers is still unknown.
Debt Service and the Operating Budget Crisis
Beyond the MTA’s huge capital needs, it already doesn’t have enough money to pay for the costs of running the system everyday. This is due in large part to debt service payments on previous capital plans. Debt service payments eat up 17% of the MTA’s operating budget now, and the MTA faces even larger out-year deficits.
Even without new borrowing, the MTA forecasts that its debt will increase 31% by 2023 and will cost more than $3.5 billion a year. A hiring freeze and cuts to staff such as subway car cleaners have meant that MTA workforce morale is low, while customers are increasingly unhappy with the quality of service. And “service guideline” cuts are on the horizon for this fall.
Will riders endure even more cuts as a result of this plan?
The operating deficit is already significant, and the MTA’s 2020-2024 capital plan outline assumes the MTA will pay for part of the plan with $10 billion in new debt. How much this debt will increase the MTA’s debt service payments, and therefore its operating deficit has not yet been explained to the public. This information is needed to understand exactly what impact the capital plan will have on the MTA’s ability to actually deliver service for its riders, its primary objective.
Real Transparency is Honesty
Reinvent Albany and our colleagues last week announced the Build Trust campaign, asking the MTA to release an implementation plan to show exactly how it will deliver on its promises, and provided a blueprint for better transparency and cost control. To us, transparency is not merely about putting more data online, but presenting real, honest information to the public.
To comply with state law, the MTA will have to hold a vote on the complete draft capital plan at its September 25 board meeting. As soon as the MTA Board receives the actual capital plan, it is required to be put it online where the public can see it. Yet with less than a week remaining before a Board vote on the $55 billion spending plan, the MTA has not released two important things: (1) the “20 Years Needs Assessment” with a detailed analysis of how much money is needed to repair the system and (2) the full, detailed list of capital projects in the proposed capital plan, with a detailed implementation plan.
When will the MTA release its 20-year needs assessment and federal TAM plan?
In theory, the MTA is supposed to follow a logical process to determine how much it needs to spend restoring the transit system.
First, the MTA is supposed to compile an inventory of its equipment and infrastructure, including the condition of its assets, and then it is supposed to compile its needs assessment of how much it will cost to repair the system so it can provide good service.
The inventory of its equipment is part of a new federal requirement called the Transit Asset Management or “TAM” plan. The needs assessment has taken the form of a 20-year needs assessment, last released in October 2013 for the last plan. Neither of these documents is publicly available for the next plan.
Without a 20-year needs assessment, or the underlying data about its assets, the public cannot know how much the MTA should be spending to replace very old, but crucial, subway and rail components, like decades old mechanical switches, electrical systems, pumps and fans. (See Reinvent Albany’s report on the MTA capital plan process.)
Decisions on capital spending don’t have to be political - they should be based on real data that takes the subjectivity out of the process.
When will the MTA release its full capital plan, with an implementation plan?
The MTA’s 11-page slideshow does not differentiate between “core” repairs versus expansion projects, lumps together costs over multiple plans, omits large capital projects, and provides no implementation schedules. This is troublesome and again raises questions about the MTA’s commitment to public transparency.
Project lists from prior capital plans have tallied more than 60 pages, itemized and coded by type of project. This allows the public to see exactly how the plan breaks out, such as how many fixes to broken equipment there are versus spending that may be more cosmetic, like the last plan’s Enhanced Station Initiative.
Expansion projects are usually expensive, representing an opportunity cost for fixes that don’t involve ribbon cuttings but are crucial like new power stations needed to run additional trains.
These lists have also included project commitment schedules, showing when the MTA intends to commit to projects (again, not spend) during the five-year window. This is the basis for developing a real implementation plan, and should be expanded upon by the MTA as recommended by the Build Trust campaign.
Before the new MTA capital plan is final, the public and stakeholders like the State Legislature -- which should hold hearings this fall before the plan is approved by the CPRB -- need a lot more detail than 11 pages to fully buy in. It is the public’s money after all, and members of the public deserve to be treated like investors who have been given a real, honest plan before staking their own money on the MTA’s future.
***
Rachael Fauss and John Kaehny are, respectively, senior research analyst and executive director of Reinvent Albany. On Twitter @ReinventAlbany.
***